THE OBJECTIVE OF THIS EFFORT IS TO REPLACE THE EXISTING MAIN SUBSTATION WITH A 69KV RING BUS FEATURING AUTOMATED SWITCHING OPERATIONS. THE NEW RING BUS WILL BE CAPABLE OF FAULT DETECTION AND AUTOMATED SELF-RESTORATION. THE PROJECT WILL BE INTEGRATED
Task order obligations
Estimated months remaining until end of performance.
Period of performance
22% of period elapsed