Average obligated amount per year since period start.
Portion of total contract value already obligated.
Share of total value represented by subawards.
1. INSTALLATION OF 10 RECEPTACLES UNDER THE FLOOR FOR 5 NEW COMPUTER RACKS. 2. INSTALLATION OF 5 NEW KOLD LOCK AIR STOPPERS IN THE RAISED FLOOR TO INCLUDE CUTTING THE CONCRETE FLOOR TILES AS REQUESTED BY MIKE MOORE.
Task order obligations
Estimated months remaining until end of performance.
Period of performance
100% of period elapsed
Awarding Agency
FMFINANCIAL MANAGEMENT SERVICE
Code: 2033
Funding Agency
FMFINANCIAL MANAGEMENT SERVICE
Code: 2033
Loading contract activity data...
Modification ID | Description | Action Date | Obligated Amount | Action Type |
|---|---|---|---|---|
Subaward # | Subawardee | Description | Amount | Action Date |
|---|---|---|---|---|