| | PROJECT UUUY191054 - INSTALL HYBRID WIND PHOTOVOLTAIC POWER PLANT, SAN VITO | BATTISTELLA S.P.A. | $586,797 | DEPT OF THE AIR FORCE | DEPT OF THE AIR FORCE | — | 236220Commercial and Institutional Building Construction | Y1MHCONSTRUCTION OF EPG FACILITIES - WIND | Sep 19, 2025 | Sep 30, 2025 | May 28, 2026 |
| | VF-06039-2P, INST. EVC STATION WIND POW. HOHENFELS | MISCELLANEOUS FOREIGN AWARDEES | $199,638 | DEPT OF THE ARMY | DEPT OF THE ARMY | — | 238990All Other Specialty Trade Contractors | Y1MHCONSTRUCTION OF EPG FACILITIES - WIND | Jun 21, 2023 | Jul 4, 2023 | Sep 30, 2028 |
| | REPLACE WIND TURBINE GENERATORS, ASCENSION AUXILIARY AIRFIELD, SOUTH ATLANTIC OCEAN | JADE CREEK CONSTRUCTION LLC | $12,271,085 | DEPT OF THE AIR FORCE | DEPT OF THE AIR FORCE | — | 237130Power and Communication Line and Related Structures Construction | Y1MHCONSTRUCTION OF EPG FACILITIES - WIND | Jul 21, 2021 | Jul 21, 2021 | Jan 30, 2026 |
| | DESIGN AND CONSTRUCTION OF THE WIND TURBINE LOCATED IN MARSEILLES, IL - $4,173,000.00 | BOYD JONES CONSTRUCTION CO | $62,902 | DEPT OF THE ARMY | DEPT OF THE ARMY | — | 236220Commercial and Institutional Building Construction | Y1MHCONSTRUCTION OF EPG FACILITIES - WIND | Jun 29, 2021 | Jun 30, 2021 | May 15, 2023 |
| | IGF::OT::IGF N-8 OUTDOOR ANNEX SEPTIC TANK CONSTRUCTION | MISCELLANEOUS FOREIGN AWARDEES | $6,041 | STATE, DEPARTMENT OF | STATE, DEPARTMENT OF | — | 212321Construction Sand and Gravel Mining | Y1MHCONSTRUCTION OF EPG FACILITIES - WIND | May 10, 2017 | May 10, 2017 | May 22, 2017 |
| | BRIDGETOWN WIND TURBINE FY 2015 IGF::OT::IGF | MISCELLANEOUS FOREIGN AWARDEES | $224,661 | STATE, DEPARTMENT OF | STATE, DEPARTMENT OF | — | 221115Wind Electric Power Generation | Y1MHCONSTRUCTION OF EPG FACILITIES - WIND | Sep 3, 2015 | Sep 3, 2015 | Sep 30, 2015 |
| | IGF::CL,CT::IGF ENERGY SAVINGS PERFORMANCE CONTRACT (ESPC) FOR THE WINDFARM PANTEX SITE OFFICE FOR PANTEX SITE OFFICE - PSO. | SIEMENS GOVERNMENT TECHNOLOGIES INC | $52,965,891 | ENERGY, DEPARTMENT OF | ENERGY, DEPARTMENT OF | — | 237130Power and Communication Line and Related Structures Construction | Y1MHCONSTRUCTION OF EPG FACILITIES - WIND | May 10, 2013 | May 10, 2013 | Jun 17, 2032 |
| | FURNISH AND INSTALL WIND TURBINE POWER SYSTEM AT BLACK BUTTE LAKE | TRI-TECHNIC INC | $302,995 | DEPT OF THE ARMY | DEPT OF THE ARMY | — | 237130Power and Communication Line and Related Structures Construction | Y1MHCONSTRUCTION OF EPG FACILITIES - WIND | Sep 24, 2012 | Sep 24, 2012 | Aug 1, 2015 |
| | ONE (1) MW WIND TURBINE | PACIFIC NORTHERN ENVIRONMENTAL LLC | $6,862,946 | DEPT OF THE NAVY | DEPT OF THE NAVY | — | 333611Turbine and Turbine Generator Set Units Manufacturing | Y1MHCONSTRUCTION OF EPG FACILITIES - WIND | Apr 27, 2012 | Apr 27, 2012 | Aug 20, 2013 |
| | DESIGN AND CONSTRUCTION OF A WIND TURBINE SYSTEM AT VA MEDICAL CENTER CHEYENNE, WY. | LEE & RYAN ENVIRONMENTAL CONSULTING, INCORPORATED | $0 | VETERANS AFFAIRS, DEPARTMENT OF | VETERANS AFFAIRS, DEPARTMENT OF | — | 237130Power and Communication Line and Related Structures Construction | Y1MHCONSTRUCTION OF EPG FACILITIES - WIND | Jan 30, 2012 | Jan 30, 2012 | Aug 12, 2013 |