Name | Type | Posted | Actions |
|---|---|---|---|
INL-25-012 MARVEL-EOI_v4.pdf | Jun 16, 2025 |
MARVEL End User Application & Utilization
Contact and place of performance
Stacie Strain
Idaho Falls, ID 83415
USA
INTRODUCTION Battelle Energy Alliance, LLC (BEA) Management & Operating Contractor of the U.S. Department of Energy (DOE) owned Idaho National Laboratory (INL), is seeking an Expression of Interest (EOI) from industry providers to suggest potential tests and experiments leveraging the Microreactor Application Research Validation and Evaluation (MARVEL) demonstration. This will consist of a two-step process starti...
View moreThe current MARVEL scope will consist of developing an 85kWth reactor producing more than 10 kWe of electricity in the first stage of operations. In the second stage, process heat (above 300°C) will be provided to end-users specifically for type 2 demonstrations from the list above. Additional information on the technical specifications can be found in the MARVEL factsheets.
SUBMITTAL REQUIREMENTS
INL is soliciting requests from private industry on potential tests or demonstrations, leveraging MARVEL, that would be valuable for them to conduct. Companies or other interested parties are encouraged to submit EOIs relating to any of the above-mentioned topical areas (or other topics not covered by the list). Expressions of Interest will be ranked based on their potential impact to the broader US energy landscape. Promising concepts will be invited to respond to a potential Notice of Opportunity (NO) at a later stage. The NO will contain additional information about requirements for a more detailed proposal, funding expectations, timeline, and proposal ranking metrics. Following selection, a two-step process is envisaged whereby stakeholders work with national lab staff first to ensure the viability of the test/demonstration (currently intended for Fiscal Year 2026). This is then followed by a solicitation to conduct physical test/demonstration (currently intended for Fiscal Year 2027-2028).
Interested entities are requested to provide expressions of interest (via email) by close-of business on 08/30/2025. Responses must include sufficient written information confirming the responder’s qualifications and the relevancy of their proposed scope based on the guidance in Section 2. Note that responses must be no more than 2 pages in length in PDF format. They should clearly state which of the above 6 category they fall under, which partnering institutions are included in the proposal, and what level of support (beyond the NO) is needed from INL (e.g., if the end-user or INL is expected to provide specific hardware). The content should ideally cover: the goal of the application, why it is impactful for the US nuclear industry, potential technical needs and technical specifications (e.g., quantity of energy needed, temperature range, MARVEL reactor operating conditions, test durations).
If you have questions, or need additional information, please contact Stacie Strain, Program Manager, via email at [email protected] with the subject line “Response to MARVEL Utilization EOI.” Technical questions must be submitted in writing via email. Only potentially qualified entities, as determined by BEA, will be contacted for further discussions or the release of a request for proposal for the project.
PROPRIETARY INFORMATION
Because information received in response to this EOI may be business sensitive or proprietary to the responding party, respondents are encouraged to minimize the inclusion of sensitive information to the extent possible and mark information in their responses accordingly.
Battelle Energy Alliance, LLC (BEA), the Management and Operating Contractor for the U.S. Department of Energy (DOE) Idaho National Laboratory, is issuing this Expressions of Interest (EOI) under solicitation number INL-25-012. The agency seeks industry suggestions for tests and experiments leveraging the Microreactor Application Research Validation and Evaluation (MARVEL) demonstration in Idaho Falls, ID. MARVEL serves as a nuclear test bed to mature novel technologies and demonstrate microreactor applications, such as nuclear-powered microgrids, data centers, chemical processing, and synfuel production. The reactor is designed as an 85kWth system producing over 10 kWe of electricity in its first stage, with plans to provide process heat above 300°C in a second stage.
The procurement follows a multi-step process beginning with this EOI to identify high-impact concepts for the U.S. energy landscape. Promising respondents may be invited to a future Notice of Opportunity. Selected stakeholders will then engage in a two-step implementation plan involving a feasibility assessment in Fiscal Year 2026, followed by physical testing or demonstration scheduled for Fiscal Years 2027 through 2028. This opportunity is classified under NAICS 221113 for Nuclear Electric Power Generation.
Responses are due by August 31, 2026, though the description requests initial expressions of interest by August 30, 2025. Submissions must be limited to two pages in PDF format and include the proposer's qualifications, the specific application category, partnering institutions, and required support from the Idaho National Laboratory. Technical details such as energy quantity, temperature ranges, and desired reactor operating conditions should also be included. Documentation associated with this notice includes one attachment titled INL-25-012 MARVEL-EOI_v4.pdf.