Name | Type | Posted | Actions |
|---|---|---|---|
Solicitation Amendment - FA664826R00030001 (1) conformed.pdf | Jun 2, 2026 | ||
NAF_Standard_Clauses_Incorporated_By_Reference_Full_Text.pdf | Jun 2, 2026 | ||
Special_Construction_Clauses_11_January NAF.docx | DOCX | Jun 2, 2026 | |
Nonappropriated_Fund_Standard_Clauses.pdf | Jun 2, 2026 | ||
KYJM23-9002 SOW (20260527) final1.pdf | Jun 2, 2026 | ||
KYJM 23-9002_AF 66 RV.xlsx | XLSX | Jun 2, 2026 | |
Background Investigation Request - BLANK base access request.pdf | Jun 2, 2026 |
Replace and Upgrade RV Storage Lot
Replace and Upgrade RV Storage Lot
The Department of the Air Force, 482 LSS LGC at Homestead Air Reserve Base, is seeking proposals to repair and upgrade an unpaved RV storage lot. This is a non-appropriated fund (NAF) procurement, funded through military community revenue rather than federal tax dollars, and is conducted as a full and open competition under NAICS code 238990. The project requires removing existing sod and topsoil, replacing base course sections, and constructing a 2.5-inch thick asphalt cement pavement across approximately 9,200 square yards. The solicitation includes a conformed SF-1442, a Statement of Work, and NAF-specific clauses. Evaluation follows a Lowest Priced Technically Acceptable (LPTA) process, focusing on price and technical subfactors such as project approach, schedule, and quality control. The estimated project magnitude is between $250,000 and $500,000, with a 180-day period of performance. A mandatory site visit is scheduled for June 10, 2026, with base access requests due by June 8, 2026. Questions are due by June 15, 2026, and final quotes must be submitted by 12:00 PM EST on June 22, 2026. The Department of the Air Force has issued solicitation KYJM 23-9002 for the repair and upgrade of the RV storage lot at Homestead Air Reserve Base. This design-build project involves geotechnical surveys, civil design, and the construction of a 2.5-inch thick asphalt pavement section over 9,200 square yards to create a stable vehicle storage surface. Conversion of approximately 9,200 square yards of unpaved surface into a 2.5-inch thick asphalt cement paved facility.
Generated by Lumen AI
Scoped analysis and attachments—go beyond the summary when you need detail from the solicitation package.
Contact and place of performance
Tahj Guilford
Homestead, FL 33039
USA
THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) Project Title: Replace and upgrade RV storage lot Project Location: Homestead Air Reserve Base, FL Project Title: NAF - Replace and upgrade RV storage lot Project Location: Homestead ARB, FL Repair and upgrade unpaved areas of RV parking lot. Remove sod/topsoil & replace sections of base course, add good...
View more1. Base Access Letters due by 09:00am - 8 June 2026
2. Site Visit: 9:30am EST - 10 June 2026 at the RV Storage Parking Area between Service Rd. and Customs Rd on Homestead ARB.
3. Questions: Due to the Government no later than 1:00pm EST- 15 June 2026. Please submit your questions electronically to: [email protected], CC: [email protected], Questions received after the requested date and time may not be considered.
4. Answers/Responses: Posted to the solicitation no later than 2:00pm EST - 17 June 2026
5. Quotes: Due to the Government no later than 12:00pm Noon EST - 22 June 2026