Name | Type | Posted | Actions |
|---|---|---|---|
SOW RML CAMPUS ELECTRICAL MAINTENANCE - ATTACHMENT C - EQUIPMENT SCHEDULES JUNE 2021.pdf | Jun 29, 2021 | ||
SF30 Amendment 01 to 75N99021R00025.pdf | Jun 29, 2021 | ||
SOW RML CAMPUS ELECTRICAL MAINTENANCE - PROJECT REQUIREMENTS JUNE 2021.pdf | Jun 29, 2021 | ||
SOW RML CAMPUS ELECTRICAL MAINTENANCE - ATTACHMENT A - TESTING REQUIREMENTS JUNE 2021.pdf | Jun 29, 2021 | ||
SOW RMLCAMPUS ELECTRICAL MAINTENANCE - ATTACHMENT B - NETA TABLES JUNE 2021.pdf | Jun 29, 2021 | ||
Solicitation 75N99021R00025 RML Campus Electrical Testing.pdf | Jun 25, 2021 | ||
SOW RML Electrical Testing.pdf | Jun 25, 2021 | ||
SOW NETA Tables and Appendix.pdf | Jun 25, 2021 | ||
SOW NETA Testing Requirements.pdf | Jun 25, 2021 | ||
SCA Wage Determination 2015-5402 Rev-11 dated 06-30-2020.pdf | Jun 25, 2021 |
Electrical Switch/Breaker Maintenance Services
Electrical Switch/Breaker Maintenance Services
Contact and place of performance
Jim Parr
Hamilton, MT 59840
USA
The Contractor shall provide all technical supervision, equipment, labor and materials necessary to perform the scope of work as described for a complete 5 Year Periodic Test, Inspection, and Maintenance of the Electrical Distribution Switchgear. Testing shall be in accordance with the latest editions of the National Fire Protection Association (NFPA); National Electrical Code (NFPA 70), Recommended Practice for Elec...
View moreThe National Institutes of Health (NIH), specifically the NIH A&E Construction office, has issued a pre-solicitation notice under solicitation number 75N99021R00025 for a five-year periodic test, inspection, and maintenance of electrical distribution switchgear. This project is designated as an SBA set-aside and is categorized under NAICS 238210, Electrical Contractors and Other Wiring Installation Contractors, and PSC H959, Other QC/Test/Inspect- Electrical and Electronic Equipment Components. The contractor must provide all technical supervision, equipment, labor, and materials necessary to perform testing and required maintenance on existing electrical switchgear, switchboards, distribution panelboards, primary oil-filled transformers, primary switches, and underground primary cabling systems.
Work is located in Hamilton, Montana, and must be performed in accordance with the latest editions of various standards, including the National Fire Protection Association (NFPA) codes 70, 70B, 70E, 99, and 101, as well as IEEE 242-2001. Performance includes complete testing and inspection protocols for the campus electrical infrastructure. Jim Parr serves as the point of contact for this requirement.
The response deadline for this opportunity is July 28, 2021. Documentation supporting the solicitation includes 10 attachments, such as project requirements, equipment schedules, testing requirements, NETA tables, and an amendment. These materials provide the detailed scope of work for the RML campus electrical maintenance and testing activities.